Civmec was contracted to provide greenfield construction works on the project, consisting of installation and pre-commissioning of pre-assembled modules, piping, electrical and tie-in works. In total, we delivered 3,750 tonnes of steel, terminated 1,600 cables, and laid more than 130 kilometres of piping, cable, cable ladder and conduit.
A collaborative and well-planned project with efficient concurrency between construction and commissioning activities, we successfully completed our works on schedule, with Roy Hill commencing full operations in June 2022.